F. STUD POCKET PREPARATION
Construct a minimum 2x4 recess designed for your
particular installation. Make sure you allow for access to
the pump in the event the unit requires service. When
constructing the framing, allow for the thickness of sub
and finish wall materials.
The unit should be installed as a recess installation. The
variety of installations possible with this unit may require
framing other than described in this manual.
1. Construct a recess with a header that is square
vertically and horizontally in accordance with
roughing-in dimensions for the unit. Do not nail
header with 2x2 brace to stud frame until after
the module is positioned in the recess. Install a
2x2 brace and toe plate around the recess opening.
2. If extra grab bars are specified: Provide 2x6
bridging or attachment at specified positions. Refer
to the grab bar manufacturer’s instructions.
NOTE: A 5” diameter opening in the floor should be
provided to permit drain connection clearance.
Nail Header
With 2x2
Brace to
Framing After
Setting the
Module In the
Recess
2x2
Braces
84-1/4”
65”
18”
38-1/8”
13”
6” Typ.
20-1/2”
63”
G. PLUMBING PREPARATION
Position the plumbing according to the roughing-in
dimensions. Cap the supplies, and check for leaks.
6. BEFORE INSTALLING UNIT
A. PARTIALLY INSTALL BATH DRAIN
Install the drain on the bath according to the drain
manufacturer’s instructions. When installing the drain
overflow tube and hood, be sure to adequately seal
along the edges of the hood to prevent leakage.
B. PROTECT WHIRLPOOL UNIT
Position a drop cloth or similar material in the bottom of
the unit. Be careful not to scratch the surface of the
product.