1. Install the Pipe Nipple
IMPORTANT! If the bath has been installed, cover it to prevent
damage to the bath surface.
Install the 1/2 pipe nipple over the pipe.
When installing the 3-way bodyspray, the pipe nipple should
extend 3/4 (1.9 cm) beyond the finished wall.
When installing the 2-way bodyspray, the pipe nipple should
extend 1/2 (1.3 cm) beyond the finished wall.
Run water through the system to flush out all dirt and debris.
Apply thread sealant to the exposed pipe nipple threads.
Finished Wall
1/2" Pipe Nipple
Apply thread sealant.
3/4" (1.9 cm)
for 3-Way
Bodyspray
1/2" (1.3 cm)
for 2-Way
Bodyspray